The Bheri Babai Diversion Multipurpose Project has sunk into limbo due to delays in starting the construction of the hydropower component despite the rapid progress made in the irrigation component. Although the multipurpose project has completed digging more than 80 percent of the 12-km tunnel, it is yet to finalise the design of the hydropower component. Bheri Babai project in limbo due to approval delays