The Upper Trishuli 3A Hydropower Project is on track to come online in a few weeks with workers putting the final touches to the power plant and the Matatirtha substation in Kathmandu.
full story »
The Kulekhani-3 Hydropower Project is finally nearing completion 11 years after construction started. Time overruns due to slowpoke contractors resulted in the 14 MW scheme missing half a dozen completion deadlines.
full story »
The much awaited Kulekhani-3 Hydropower Project has again missed its completion deadline of January 2019 due to the dillydallying by a Chinese contractor hired for the job.
full story »
The construction of the much-delayed Kulekhani-3 Hydropower Project has slowed to a crawl due to the poor performance of the contractor hired to implement the electromechanical works.